Here is the Carson City area road report for the week of August 16-22, 2021. Closures are expected at the following locations due to road and utility work:
— Curry Street between 2nd Street and 5th Street will be closed, Monday through Thursday, 7:00am to 5:30pm for road construction. Pedestrian detours will also be in place. Please plan accordingly.
— Fairview Drive will be closed in the southbound direction only, August 15th, 7:00am to 5:00pm for paving. Northbound traffic will remain open.
— Kings Canyon Road west of Longview Way will be closed 7-days a week, all day, for roadway reconstruction. Only local residential access will be provided. The Waterfall Trailhead and parking area is also closed until further notice. Please do not come up Kings Canyon at this time. Instead, please use one of the many other wonderful open space areas in Carson City such as the Carson River area or Prison Hill.
— Northridge Drive between Table Rock Drive and Ridgecrest Drive will have single lane closures with flaggers, Monday through Friday, 7:30am to 5:00pm for construction of a concrete barrier rail. There will be intermittent closures at the intersections of Northridge Drive at Wilma Way and at Ridgecrest Drive. Please follow detour routes and plan accordingly.
Lane restrictions are expected at the following locations due to road and utility work:
— Long line and short line striping and painting will take place citywide, Sunday through Friday, 8:00pm to 6:00am. Please use caution and do not pass painting trucks. Also, please do not drive in wet paint.
— Carson Street at Stewart Street will be flagger controlled, Monday and Tuesday, 8:00pm to 6:00am for a re-striping project. Please expect delays and consider an alternate route.
— Curry Street at Rhodes Street will have a lane shift with cones on Tuesday, 10:00am to 3:00pm for a sewer project. Please use caution and follow all roadwork signage.
— Fairview Drive between E. 5th Street and Butti Way will have shoulder work, Monday through Friday, 7:00am to 5:00pm for utility construction. The multi-use path will be closed. Please use caution and follow all roadwork zone signage.
— Gentry Lane between Hudson Drive and Snyder Avenue may have lane restrictions with flaggers, Monday through Friday, 7:00am to 4:30pm for a utility replacement project.
— Long Street between Roop Street and Rand Street will be reduced to one lane with flaggers, Monday through Thursday, 7:00am to 5:30pm for roadway reconstruction. Please expect delays and consider an alternate route.
— Northridge Drive between Eastridge Drive and Carriage Crest Drive will be reduced to one lane with flaggers, Monday through Wednesday, 7:00am to 6:30pm, and Thursday through Friday, 7:30am to 5:00pm for a roadway reconstruction project. There will be intermittent closures at the intersections of Northridge Drive and Carriage Crest Drive, Spooner Drive, and Eastridge Drive. Please use caution and follow marked detour routes.
— Rand Street between William Street and Camille Drive will be reduced to one lane with flaggers, Monday through Thursday, 7:00am to 5:30pm for roadway reconstruction. Please expect delays and consider an alternate route.
— Roop Street between Corbett Street and Washington Street will be reduced to one lane in the northbound direction, Monday through Friday, 8:00am to 4:00pm for an electrical project. Additionally, the northbound shoulder will be closed north of William Street. Please use caution and follow all roadwork signage.
— Saliman Road at Long Street will be flagger controlled, Monday through Thursday, 7:00am to 5:30pm for roadway reconstruction. Please expect delays and consider an alternate route.