Here is the Carson City area road report for the week of July 20-26, 2020. For information on lane restrictions and street closures related to the South Carson Street Project, visit CarsonProud.com.
The following schedule is for the South Carson Street Project. Construction is on schedule. SNC is preparing the groundwork for the roundabout with an anticipated Carson Street and Stewart Street intersection closure in August. The construction map has been updated to reflect July 20-24 cone zone.
— Fifth Street to Stewart Street one lane in each direction will be open, the cone zone will remain in place around-the-clock.
— Stewart Street at the Carson Street intersection will be closed in both directions.
— Frontage Road is open to two - way traffic with temporary driveway closures.
— Fairview Drive: one lane in each direction will be open around-the-clock.
— Clearview to Fairview: one lane in each direction, the cone zone will remain in place around-the-clock.
— Rhodes to Fairview: east side roadway work.
Elsewhere, the following closures are expected at the following locations due to road and utility work:
— Airport Road remains closed in both directions between Woodside Drive and Menlo Drive for installation of new sewer and water utilities. Airport Road will also remain closed to through traffic between US 50 and Woodside Drive, Monday through Friday, 7 a.m. to 5:30 p.m. Residential and business access will also be allowed. JAC service will continue; however, detours will be in effect.
— Retail Court will be closed east of College Parkway, Monday through Friday, all day. Access to the businesses will be maintained. There may also be periodic closures and detours to the multi-use path between Emerson Drive and Retail Court.
Lane restrictions are expected at the following locations due to road and utility work:
— 2nd Street, 3rd Street, and Valley Street will have single lane closures while crews reconstruct the parking lot along Stewart Street, Monday through Friday, during daytime hours.
— Airport Road will have flagger controls between Minonee Lane and Menlo Drive, Monday through Friday, 7 a.m. to 5:30 p.m. while crews temporarily patch portion of the road.
— College Parkway will have a single lane closure in the westbound direction between the I-580 Interchange and Retail Court for construction associated with the adjacent development, Monday through Friday, 9 a.m. to 3 p.m. The lane closure may extend up the interchange ramps.
— Fairview Drive will have continued eastbound and westbound single lane closures while utility work and roadway reconstruction occurs, Monday through Friday, 7 a.m. to 5:30 p.m.